Includes | administrative and procedural requirements for scheduling, recording, and reporting progress. |
May Include | construction schedule form. Work plan schedule form. Construction equipment form. Other appropriate forms. |
Alternate Terms/Abbreviations | CPM: critical path method. |
See | 00 31 21 for survey information provided to bidders or proposers. 00 43 83 for proposed construction schedule form. 00 43 86 for proposed work plan schedule form. 01 71 23 for field engineering during construction. 01 78 29 for final site survey. |
See Also | 00 62 83 for construction schedule form. 00 62 86 for work plan schedule form. |